(更新施作時間)(Revised Construction Schedule)B棟五樓電氣設備更換

 

施工項目:(更新施作時間)B棟五樓電氣設備更換

 

施工日期:2026年11月01日(星期日)

施工時間:08 :00至17 :00。(提前完工,提前復電)

施工位置:B棟五樓電氣機房。

 

停電範圍:

B棟頂樓:380/220V一般電源

B棟七樓:380/220V一般電源

B棟五樓:全面停電(380/220/110V一般電源、緊急電源均停電)

B棟三樓:380/220V一般電源

B棟一樓:380/220V一般電源

 

注意事項:施工期間會有部分區域停電,施作過程可能有噪音、震動等。如有不便敬請見諒。

施作廠商:承紳科技 黃先生 0910-228-381

 

(Revised Construction Schedule)

Electrical equipment replacement on the 5th floor of Building B

Date: Sunday, November 1st, 2026

Time: 8:00 AM – 5:00 PM (Early completion, early restoration)

Work Location: Electrical room, 5th Floor, Building B

《Affected Areas》

  • Building B, Rooftop Level: 380/220V normal power
  • Building B, 7th Floor: 380/220V normal power
  • Building B, 5th Floor: Complete Power Outage (380/220/110V normal power and emergency power will be shut off)
  • Building B, 3rd Floor: 380/220V normal power
  • Building B, 1st Floor: 380/220V normal power

 

【Please Note】: Power will be shut off in some areas of the building during the work. Noise and vibration may occur. We apologize for any inconvenience.

Contractor: Mr. Huang  0910-228-381